South Eastern Railway

RSI Analysis at Br No. 187 (2x12.2 M CG) in BLDA-DNT & 03 bridges in SFO-RVNL at Br. No. 332 (7x12.2M CG), Br. No. 336 (6x12.2M CG) & Br. No. 338 (4x12.2M CG) for construction 3rd Line between Narayangarh - Bhadrak.

Completed

Western Railway

Detailed structural design and drawings for substructure and foundation of Important Bridge No. 813 Narmada Bridge between BWW-OM section of RTM division.

Completed

Central Railway

Design and drawing for Major Bridge No. 1031/2 (ROR), Major Bridge No. 833/1, RUB Br. 1041/3, RSI analysis of Br. No. 833/1 in connection with Itarsi-Nagpur 3rd Line.

In Progress

North Central Railway

Rail Structure Interaction (RSI) Analysis of composite Girder Bridges of Jhansi Division (4 Nos).

Completed

RVNL Nagpur

Design of Major Bridges/ Minor Bridges/ ROBs/ RUBs/ Aqueduct, etc. from km 190 to km 207 in YTL-NED Project.

In Progress

Rites Limited, Mumbai

Instrumentation for RSI analysis of track bridges No. 428 (Span: 2x18.30m) Section Virar-Surat.

In Progress

Central Railway

Design and Drawing of important Bridge No. 836.1, 7/30.5m Composite Girder in connection with Itarsi-Nagpur 3rd & 4th line.

In Progress

Western Railway

Design & Drawings of retrofitting scheme for distressed substructure and foundation of bridge No. 374 (15x30.5m) of Udhna-Jalgaon section of Mumbai Division.

Completed

Western Railway

Design & Drawings of retrofitting scheme for distressed substructure and foundation of bridge No. 130 (11x30.5m) of DB CTD Section of BRC Division.

Completed

IIT, Guwahati

Instrumentation of superstructure using strain gauges, displacement transducers, and accelerometers of various spans between Garhwa Road and SoneNagar of East Central Railway.

Completed

Central Railway

RSI analysis of composite Girder Bridge 293/1 (7x18.3m) in Nandgaon-Pimparkhed section in connection with Manmad-Jalgaon 3rd line Project.

Completed

Western Railway

Load testing and instrumentation of U type PSC girder of 18.3m span of Major Bridge No. 437 between BRLA-NLI section in connection with doubling project of NMH-RTM section in Ratlam Division.

Completed

Western Railway

Instrumentation and continuous monitoring of pier P5 to P9 of bridge no. 130 (11x30.5m) of Dabhoi-Alirajpur section of Vadodara Division.

In Progress

Western Railway

Instrumentation and continuous monitoring of pier P8 to P11 of bridge no. 374 (15x30.5m) of Udhna-Jalgaon section of Western Railway.

In Progress

NHAI Patna

Design of retrofitting scheme of the superstructure of ROB @ 177+182 and Major bridge over Gandak @ 206+436 of 4 laning of Chhapra-Hajipur section on NH-19.

Completed

Eastern Central Railway

Consultancy work on Rehabilitation of ROB BEA (Bow String Girder) between stations KRS-BEA in PNBE-DDU section of Danapur Division.

In Progress

NHAI Ranchi

Design of Strengthening scheme of continuous PSC Girders (80m) by CFRP of Telmacho Bridge under Govindpur (Rajganj)-Chas-WB Border section of NH-32, Jharkhand.

Completed

H. G. Infra Engineering Ltd.

Adequacy check for existing Arch bridge No. 373/2, 373/3 & 374/1 of Central Railway.

Completed

Sannverse Railtech Pvt. Ltd., Hyderabad

GAD, Structural design and drawings of bridges of 3rd line construction between Jujharpur to Dharakoh (excluding station yards) on Itarsi-Nagpur Section of Central Railway.

In Progress

Sri Durge Condev Pvt Ltd

Detailed design and drawings of Railway Bridges, ROBs, RUBs and other structures between Srirampur and Pallahra Road stations of Talcher-Bimalagarh New BG Rail link project of ECOR.

Completed

South Eastern Railway

Rail structure interaction (RSI) analysis for bridge Nos. 199–206 of Narayangarh-Bhadrak section (construction of 3rd line) of Kharagpur division.

Completed

MRVC Mumbai

Rail Structure interaction (RSI) analysis of bridge No. 73 and 75 located between Bhayandar and Naigaon Stations of Mumbai Division.

Completed

Western Railway

Investigation of strength of existing substructure of bridge No. 624 UP (8x64m) of Vadodara Division.

Completed

NHAI Patna

Preparation of DPR for blackspots on NH-19 of Chhapra–Hajipur Section.

In progress

East Central Railway

Checking adequacy and designing strengthening scheme of the welded bow sting girder of ROB at Bhabua Road station limit and Kudra station of DDU Division.

In progress

East Coast Railway

Rail Structure Interaction Analysis of bridge No.92 of Jarpada–Budhapank 3rd & 4th lines.

In progress

ISC Projects Pvt Ltd

Design of Launching scheme of Bridge No. 627/1 (4x76.2m) OWG between Amalakhurd and Tukaithad Stations of Nanded Division of SCR.

In progress

Central Railway

Design of important Bridge No. 835/2 (9x30.5m) Composite girder in connection with Itarsi–Nagpur 3rd & 4th line.

In progress

Western Railway

Rail Structure Interaction (RSI) analysis and providing suitable modification/strengthening for continuation of LWR for Important Bridge No. 85 (15x18.30m) composite girder of HMT–KDBM Section.

In progress

Northern Railway

Rail–Structure Interaction Analysis of Railway Bridge No. 75 (14×30.5m) Composite Girder in Jaunpur–Zafarabad Section of Lucknow Division.

In progress